Building Construction in Dhaka City needs legal permission from Rajdhani Unnayan Katripakkha(RAJUK). The new DAP: 2022-2035 covers about 1528 Square Kilometers of land. If we want to build our house within the territory of RAJUK, we have to take 02 separate permissions from RAJUK.
Sometimes, the entire process becomes very complicated and time-consuming for individuals. We at Build-Tech Engineering, have made the process hassle-free. We collected all required papers from the Landowners. Our legal team checked and verified all of them. Finally, we put up all documents on the servers. Generally, we offer a turnkey basis approval process to the landowners.
We offer the following services regarding RAJUK Approval:
RAJUK Plan Approval Process requires two permissions.
Firstly, The Land Use Clearance. It is abbreviated as LUC.
Secondly, The Construction Permit.
RAJUK launched the Electronic Construction Permitting System in 2024. Shortly it is known as ECPS permit. In ECPS, land use clearance is renamed as “Planning Permit”. To get a construction permit, 04 drawings must be submitted to RAJUK.
These drawings are prepared according to the New DAP:2022-2035. Either an Individual Landowner or a Developer Company must take plan Approval before starting any construction. The whole process of Plan Pass Process is described below:
It is an automated and online process. You need to submit an online application to the Town Planning Department in RAJUK. The prescribed form is (Form No-101).You have to apply through the ECPS official website. Digital signed by the owner of the Land to be uploaded. You can engage any other authorized person to do the application process. The Planning Permit is slightly different for Private Land, Housing Plot, and RAJUK Plot.
After getting Land use clearance approval, you have to apply for a Construction permit. You have to submit an online application Form (Form-301) through the ECPS website. You must submit your plan within the validity period of LUC of 24 Months. <br>The whole Process of the RAJUK Plan Approval and Construction Permit are described below:
The Architect should have the following qualifications if they want to prepare the RAJUK Approval Drawing Sheet and Sign on it-
The Structural Engineer can conduct the Structural Analysis & Design Works as well as sign-on Approval sheet if they have the following qualifications-
Layout Plan in 1:200 Scale with the following information
Some projects are called special projects or large projects in DMINB-2008. This type of project needs special project permission from the Special Project Approval Committee of RAJUK. For special project permission, an application is to be submitted through the special project Approval Form (Form-201). This is the last step of the RAJUK Plan Approval Process for the Construction Permit.
The above RAJUK Plan Approval Process for Construction Permit in Dhaka city is time-consuming and tiresome. There are so many Architectural Firms in Dhaka to guide you to get your plan approved easily. Carefully choose a reputed and professional firm to expedite your whole process. We at Build-Tech Engineering, have been working in this field for more than 05 years and completed about 110 projects successfully.